250 applications. 800 servers. One Day 1 that had to work.
- IT Carve-Out
- Utilities
How an entire mining & generation business left a European energy group — with its IT rebuilt from data center to desktop, and the trading systems ready on Day 1.

Proof point
What we delivered
- Clients & Workstations
- ~4,000
- IT sub-projects
- 11
- Person-days planned
- ~40 000
- Months from closing to full separation
- 24
“The hard part wasn’t separating the IT. It was keeping both businesses fully running through every second of the split.”

Bapo Wachs
Managing Partner
The situation
Why an entire company had to leave the group
When a European energy group sold its lignite mining & generation business, an entire company had to leave a deeply integrated group IT: around 250 applications — SAP ERP with 280 interfaces, HR and payroll, plant and market systems — plus 800+ servers, 771 TB of data and thousands of workstations, all run centrally by the group.
The challenge
Keeping two businesses running through the split
Keep two businesses fully operational at every moment of the separation — seller and carve-out alike. Trading applications could not be shared even for a day, so they had to be physically separated and stand-alone before closing. And the new company needed its own data center, network, licenses and IT contracts — from a standing start.
Our approach
How we deliver a large-scale IT carve-out
Two-phase model
A two-phase model: logical separation by closing, full physical separation within a ~24-month TSA phase — every service governed by TSA and IT contracts until cut-over.
Day-1 readiness
Day-1 readiness for the trading systems: physically separated and operational at closing.
Master plan
A master plan across 11 IT sub-projects, with integrated planning, a joint risk map maintained with the buyer, and change-request discipline.
Migration strategies
Application-by-application migration strategies (copy & delete, lift & shift, install & migrate) instead of one-size-fits-all.
Infrastructure & licensing
A new data center sourced as managed services via competitive (EU) tender — stand-alone infrastructure without building an IT organization from scratch on Day 1. License economics assessed per vendor (transfer vs. repurchase over a 5-year horizon), cutting the license cost estimate by more than a third.
The result
The business went live as a stand-alone company: own data center, own network, own SAP landscape, own contracts — while both sides kept operating without interruption. The largest carve-out our team has managed to date.