400 applications. 2,800 clients. Zero missed milestones.
- IT Carve-Out
- Utilities
How a city's district heating utility left an international energy group — with its entire IT rebuilt, on schedule and 20% under budget.

Proof point
What we delivered
- Milestones met
- 100%
- Under budget
- −20%
- Clients migrated
- ~2,800
- IT sub-projects
- 9
“The pandemic wasn’t the hard part. The hard part was rebuilding 400 applications 1:1 — with not a single functional change.”

Sebastian Gieser
Managing Partner
The situation
Why the IT had to leave the group
When a metropolitan district heating utility was sold back into municipal ownership, its entire IT had to leave the parent group: the utility ran no IT of its own — every system, from SAP ERP, HR and IS-U billing to grid and process control applications, was embedded in the seller's group landscape.
The challenge
Delivering a separation through a pandemic
Around 400 applications and 2,800 workstations had to be separated and rebuilt at the new IT provider — with no functional changes allowed (1:1 principle), audit-certified migration of all finance-relevant systems, GDPR-compliant data transfer, and hard dependencies on two business-critical parallel programs at the seller. Then, midway through: COVID-19.
Our approach
How we deliver an IT carve-out
Separation roadmap
A separation roadmap (“string of pearls”) answering one question early: which application moves when — frozen, then managed strictly by change request (55+ CRs, none of which delayed the end date).
Integrated planning
Integrated project planning across 9 IT sub-projects, each staffed three-way: seller, buyer, future IT provider.
Compliance & Audit
A standing data-release board with IT security, information security and data protection — GDPR compliance built into every migration. Auditor-attested migrations (IDW PS 850) for SAP ERP, HR and IS-U.
TSA & contract framework
TSA and IT-contract framework governing every service until cut-over.
End-user communication
Dedicated end-user communication from day one — flyers, trainings, no surprises.
The result
Every milestone was met — user accounts, client rollout, application moves, mailbox and file migrations, full physical network separation — despite the pandemic forcing the project remote. Final cost came in about 20% below the original estimate.